Where the week goes

StepTypical timing
Photo and indicative priceSame day
Site inspection and fixed quote1 to 3 days
Ausgrid notification and scheduling3 to 5 business days
The work1 day, outage of 2 to 4 hours
CCEW and close-out1 to 2 days

What makes it longer

  • Storm season, when every Level 2 on the Coast is booked
  • Rock in the footing, which can add half a day
  • Traffic control approvals for street-side poles
  • Discovering the service line or meter panel also needs work

What makes it shorter

  • An urgent defect notice, which we prioritise
  • Good access and a standard pole
  • Having photos ready on the first call