Start with the numbers

ChargerSupply neededRange added per hour (approx.)Overnight (8 hrs)
7kWSingle phase, 32A circuit40 to 50 km320 to 400 km
11kWThree phase, 16A per phase60 to 75 kmFull from empty
22kWThree phase, 32A per phaseUp to 130 km (car permitting)Full in 3 to 4 hrs

Most EVs on Australian roads cannot accept more than 7 to 11kW from a home AC charger anyway. A 22kW wall box charging an 11kW-limited car delivers 11kW. Check your car's onboard charger rating before paying for capacity it cannot use.

What matters more than phases: headroom

The real question is whether your existing supply has room for another 32A continuous load. A charger runs for hours at full draw. If your home already has ducted air, an electric hot water system, a pool pump and an induction cooktop on a single-phase 63A or 80A supply, adding 32A can push the main switch or the consumer mains past what they were sized for.

That is a load assessment, and it is the first thing we do. Sometimes the answer is a smarter charger with dynamic load management, which throttles itself when the house is busy. Sometimes it is bigger consumer mains. Occasionally it is three-phase.

When three-phase is the right answer

  • Two EVs charging at the same time, regularly
  • A car that genuinely accepts 22kW and you need fast top-ups
  • A workshop, granny flat or large shed on the same supply
  • You are already planning a big solar and battery system
  • The existing single-phase mains are undersized and need replacing anyway, so the extra cost of going three-phase is marginal

What a three-phase upgrade involves

New three-phase consumer mains from the street, a switchboard that can take three phases, a three-phase smart meter, and rebalancing your circuits across the phases. It is Level 2 work with an Ausgrid notification, a planned outage of a few hours, and a CCEW at the end. From about $4,800 on the Central Coast, more if the switchboard is old. See metering and three-phase upgrades.

The Level 2 angle most installers miss

A lot of EV charger installers are general electricians. If your job needs new mains or a meter change, they have to bring in a Level 2, which means a second trade, a second visit and a second invoice. Because Anaconda is a Level 2 ASP, we quote the charger and any supply work together. Details on the EV charger page.